Timeline for big.LITTLE Fast Model

Milestones Status

Plan of Record

Milestone

Date

Current

Last Report

Issue

Develop Reference Switcher

3/15/2012

Debugging Switching Errors

Validation Ready

3/29/2012

All resources on board

Validate Ref. Switcher

4/5/2012

Resources

Develop Integrated Switcher

4/05/2012

New code

Validate Integrated Switcher

4/26/2012

Develop RC-1

5/10/2012

GA Release

5/30/2012

Color Keys

Complete

On target

At risk
mitigation in place

Will miss target
Immediate action required

Blueprints Status

Accomplishments This Week

  • Test Plan ready for review an approval
  • Reference code has improved, many fixes from ARM, but still not work perfectly. testers can start using it to integrate some tests, but to do real testing yet.

Issues

  • License infrastructure being setup
  • Resources issue moved from Red to Yellow, platforms assigned resources, KWG may be able to provide - Resource issue has been resolved.

Big.Little.Switcher/WeeklyReports/2012-03-01 (last modified 2012-03-07 19:59:21)