Release Schedule

The main stages of the Linaro 10.11 release are as follows:

Stage

Expected

Explanation

Alpha 1 Release

2010-06-03

First alpha of 10.11 Linaro release

Feature Definition Freeze

2010-06-17

All prospective features will be defined and acknowledged by the release team.

Import Freeze

2010-06-24

All packages from Ubuntu and the Working groups will be imported.

Alpha 2 Release

2010-07-01

Second alpha of the 10.11 Linaro release.

Alpha 3 Release

2010-08-05

Third alpha of the 10.11 Linaro release.

Feature Freeze

2010-08-12

All proposed features will either be at a beta or postponed stage.

Beta Freeze

2010-08-26

From now on all uploads to the main Linaro archive will have to be approved by the release team.

Beta Release

2010-09-02

Beta of the 10.11 Linaro release.

Final Freeze

2010-09-16

From now on all changes to the archive must be approved by the release team. Only critical bugs will be fixed.

Release Candidate

2010-11-01

Complete, stable and ready to test by any user. Ideally very little changes happen between this and the final release.

Final Release

2010-11-10

Final version of the Linaro 10.11 release.

Adding New Features

From feature freeze onwards, no new features will be added to the release. At that time it is expected that any new features are substantially complete and ready for testing. Feature freeze allows widespread user testing, feedback and bug reports to be generated and gives developers the time to respond before the final release. By feature freeze, software should have all new features developed, be testable and integrated into the release.

Cycle Milestone Descriptions