Parent

Graphics WG Dashboard

Status period: wk05.2012 (20120130-20120203)
Previous weekly report

Project name: Graphics WG Q1.12
Target release: 12.02
Overall status: {OK}
Project trend: {OK}

Tech. lead: Jesse Barker <jesse DOT barker AT linaro DOT org>
Project manager: Ilias Biris <ilias DOT biris AT linaro DOT org>
Target component release date (CRD): 16 Feb 2012
Days remaining to CRD: 13

Blueprints quick links

Quick status

Baseline

Forecast

Overall project information

Add ShaderSource object to reflect its commonality across projects

(./)

16.02.2012

16.02.2012

Achievements
- 12.01 release completed, 3 out of 6 blueprints completed, 2 Lava related blueprints moved to 12.02 (see the planned blueprints on the left side of this table - both those blueprints are still in need of infrastructure), and the dma-buf + v4l2 as a user blueprint was put on hold since there is discussion ongoing related to the evolution of dma-buf
- Worked to resolve issues for the Nux/Compiz/Unity release, Unity with gles2.0 branch was approved and on its way to be merged
- Fixed display issue when playing two desktop scenes in a row, exposed by the canvas-reset branch functionality

Update local version of libmatrix for glmark2

(./)

16.02.2012

16.02.2012

Update local version of libmatrix for glcompbench

(./)

16.02.2012

16.02.2012

Issues
- Dashboard bugs: #881789 - timeout in image deployment and #904796 - provide staging/development lava server instances are a still there and pose a risk for our work with the LAVA dashboard for glmark2 tests
- The following issues need to be addressed for 12.02 release:
+ compiz issues (eg organize and prioritize the "refactoring" - chunking it down into manageable patches - of the compiz changes so we can move forward sanely)
+ upstream (e.g. dmabuf) review cycles
+ data publishing policy and what it means for our dashboard work

Get the Linaro Graphics WG tests running on a daily basis

{X} needs infrastructure to complete (related to bug #881789 timeout in image deployment)

16.02.2012

16.02.2012

Risks
- Even though there are actions now taken to deal with Unity/Nux/Compiz, it is possible that those packages are have issues which may require more time for the release
- If the dashboard related bugs are not resolved during Connect it will be once again necessary to move those blueprints forward. This would be the 3rd milestone in a row where we move those blueprints, so we should work together with Validation team to make sure the bugs are resolved
- Due to the current process of discussing the evolution of dma-buf with upstream (DRM and V4L2 communities) it is very probable to not have something ready for dma-buf for 12.02, we would then target 12.03 instead

Visualize glmark2 results in dashboard

{X} needs infrastructure to complete (related to bug #904796 - staging/dev lava instances needed)

16.02.2012

16.02.2012

Key decisions and change requests

Status indicators

Next steps
- Connect - subscribe and follow the Graphics and Multimedia sessions
- Work is progressing for the 12.02 release, and at least one side of the work is implemented (updating libmatrix and also the components which use it - glcompbench and glmark2)

{OK} : project status and trend is OK
(./) : Delivered
{X} : Blocked or dropped (clarification with indicator). Information as to what is blocking the work should be in the Blueprint
IconsPage/icon-milestone-16x16.png : Work in Progress now
/!\ : Work at risk

WorkingGroups/Middleware/Graphics/Status/2012-02-01 (last modified 2012-02-03 09:42:08)