Multimedia WG Dashboard

Status period: wk02.2012 (20120109-20120113)
Previous weekly report

Project name: Multimedia WG Q4.11
Target release: 12.01 and 1.1.90-2012.01 (LJT) and 12.01 (UMM)
Overall status: {OK}
Project trend: {OK}

Tech. lead: Tom Gall <tom DOT gall AT linaro DOT org>
Project manager: Ilias Biris <ilias DOT biris AT linaro DOT org>
Target component release date (CRD): 19 Jan 2012
Days remaining till CRD: 3

Blueprints quick links

Quick status

Baseline

Forecast

Overall project information

Audio for Panda with Linaro LEB "Just Works"

NS

19.01.2012

19.01.2012

Achievements
- libjpeg-turbo: updated android code to latest, tjunittest (1 failure), tjbench, skia-bench. skia-bench not great, new blueprint created to address (565 and 8888 unoptimized), looking at past qualcomm code.
- linarotv-xbmc live-config building successful. bp complete.
- For DRM : moved to 12.04 / armhf fs, rebuild xserver 1.12 RC1 and related trees rebase and resubmitted final version of few omapdrm patches for api changes coming in through drm-next (drmplane/addfb2) and fbdev-next (omapdss fifomerge api changes)
- Added ucm configs for mx53 HDMI card, added channels and priority properties in ucm4pa code. Also added priority to ucm config for mx53 to make analog jack the default sink
- CMA LAVA test running - but also needs to be split into multiple shorter tests, as it runs out of time
- Porting capture to tinyalsa for e2e audio test support
- Created a git repo for the Speex release for Android (speex_linaro_android.git under ronynandy in git.linaro.org - there is a problem preventing it to show properly in gitweb - now being solved by IS)

Audio for Panda with Linaro Android ICS "Just Works"

19.01.2012

19.01.2012

UCM for Android

IconsPage/icon-milestone-16x16.png (has split into the basic support for Android, and the work for the common configuration formats between Android and Ubuntu)

19.01.2012

19.01.2012

End to end audio testing lava integration

NS

19.01.2012

16.02.2012

Implementation of dri2proto support - xf86-video-omap

IconsPage/icon-milestone-16x16.png

19.01.2012

19.01.2012

End to end audio testing prototype on Android

{X} (blocked on bug #893402)

19.01.2012

16.02.2012

Issues
- Bug #893402 is impeding progress in end-to-end audio testing (only a prototype is available for desktop - pandaboard is not functional). We're working on the bug, the focus has passed to alsa-lib, pulseaudio and the UCM configs
- #911860 Android NEON detection is busticated - working on it now
- #912035 - Android: skia-bench segvs - Fix Committed
- #898395 - jpegint.h missing in -dev package - Fix Committed

End to end audio testing prototype on pandaboard

{X} (blocked on bug #893402)

19.01.2012

16.02.2012

Speex codec - LAVA benchmarking

IconsPage/icon-milestone-16x16.png

19.01.2012

19.01.2012

UCM for Pulseaudio upstream and testing activities - 11.12

IconsPage/icon-milestone-16x16.png

19.01.2012

19.01.2012

RealVideo NEON optimization

IconsPage/icon-milestone-16x16.png

19.01.2012

19.01.2012

Risks
- Due to time shortage, it is possible that some codec optimisation work will come in 12.02

AAC NEON optimisations in libav

NS

19.01.2012

16.02.2012

Optimise XBMC run on LEB

IconsPage/icon-milestone-16x16.png

19.01.2012

19.01.2012

gstreamer replacement of xbmc dvdplayer

NS

19.01.2012

16.02.2012

libav vp8 optimization

NS

19.01.2012

16.02.2012

Evaluate ICS jpeg for updated upstream code

IconsPage/icon-milestone-16x16.png

19.01.2012

19.01.2012

Key decisions and change requests

Tune Skia Bench usage of libjpeg-turbo

(./)

19.01.2012

19.01.2012

Brush up 565, add test cases for android merge

IconsPage/icon-milestone-16x16.png

19.01.2012

19.01.2012

Merge JCS_RGBA_8888 into JCS_EXT_RGBX

IconsPage/icon-milestone-16x16.png

19.01.2012

19.01.2012

Add tjunittest + media into LAVA

IconsPage/icon-milestone-16x16.png (will split into a part coming in 12.01 and another part will come in 12.02)

19.01.2012

19.01.2012

Status indicators

Next steps
- Proceed with the release tasks for 12.01. Continue planning for Connect - see the preliminary MMWG plan for LCQ1.12

{OK} : project status and trend is OK
(./) : Delivered
{X} : Blocked or dropped (clarification with indicator). Information as to what is blocking the work should be in the Blueprint
NS: Not started
IconsPage/icon-milestone-16x16.png : Work in Progress now
/!\ : Work at risk

WorkingGroups/Middleware/Multimedia/Status/2012-01-10 (last modified 2012-01-16 11:59:36)